Duration Column with Dependencies Enabled
Hi All,
So with the duration column, we have decided to enable the dependencies however the calculation seems a bit off
To test it we but in 2 days for duration
Dependency is Start Date and Due Date
We thought that if the Duration is two days. We put in a Start Date of 9/1/2020, then the Due Date should be 9/3/2020. Instead it is as if Smartsheet counts the date entered as a whole day when the day should begin the next full day.
Any tips or feedback is greatly appreciated!!!
Best Answer
-
Your start date is considered one of those days, so the 1st 8 hours (1 day) is the actual start date.
So 16 hours = 2 days.
Day 1 = 09/07/20
Day 2 = 09/08/20
24 hours is 3 working days.
Day 1 = 09/07/20
Day 2 = 09/08/20
Day 3 = 09/09/20
Based on your screenshots, the dates are accurate, but based on your explanations you are actually wanting to start the day after the date in your start date column.
Answers
-
Hi @Leslye Jackson,
why don't you enter the actual start date?
Start date is a full 8 (or whatever) hour working day. So if you say the task takes 2 d, that's 16h in your settings and this results very correct in the two days 1. + 2. of September being used.
Hope this helps
Stefan
Smartsheet Consulting, Solution Building, Training and Support.
Projects for Processes and for People.
-
@Stefan Thank you for your feedback so I tried that but it literally didn't change the results. I put in 24 hrs and it counted two days.
-
Your start date is considered one of those days, so the 1st 8 hours (1 day) is the actual start date.
So 16 hours = 2 days.
Day 1 = 09/07/20
Day 2 = 09/08/20
24 hours is 3 working days.
Day 1 = 09/07/20
Day 2 = 09/08/20
Day 3 = 09/09/20
Based on your screenshots, the dates are accurate, but based on your explanations you are actually wanting to start the day after the date in your start date column.
-
Thank you so much for your feedback on this!! All of you guys rock!!!
-
Happy to help. 👍️
-
Hi @Leslye Jackson ,
also happy to help!
As @Paul Newcome already pointed out, the dates your sheet shows are correct.
The connection between the figures in DURATION and the start/end date is determined by the section "Working days" in your project settings. Everything you change there influences the calculation of the end date.
For a deeper understanding you may check these articles:
Greetings
Stefan
Smartsheet Consulting, Solution Building, Training and Support.
Projects for Processes and for People.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives