Duration Column with Dependencies Enabled

Hi All,

So with the duration column, we have decided to enable the dependencies however the calculation seems a bit off

To test it we but in 2 days for duration

Dependency is Start Date and Due Date

We thought that if the Duration is two days. We put in a Start Date of 9/1/2020, then the Due Date should be 9/3/2020. Instead it is as if Smartsheet counts the date entered as a whole day when the day should begin the next full day.

Any tips or feedback is greatly appreciated!!!



Best Answer

Answers