How to get a value from a precedent task in a project ?
Hello everyone
I have an issue with a formula in a metric sheet. Here is my use case : I have a sheet with a project, divided into 5 tasks. For each task I have a column "value" with a different value. I only put the value of a task when I finished the task : I call it "real value".
I want to have the following information for "theoritical value" : the theoritical value is the value of a task that is not completed, and it's value is the real value of the precedent task.
So if I have 600 in task 2 that is finished, and I am in task 3 that is in progress, the theoritical value of task 3 should be 600, until I put a real value when I finish the task 3.
Do you know how I could get the value of a precedent row, because I made a SUMIFS formula but the formula only verify criterias and sum values on the row of the actual task ?
Thank you very much !
Have a great day,
Corentin
Answers
-
Hi there @Corentin Dal Farra ,
Are you able to share a screenshot(s) of your current Sheet Set-up, whilst removing sensitive data? From here, we should be able to create a Formula to fit this scenario
Regards
Sean
-
Hello @Sean Morgan
I have found a solution about this, I have just made a = formula that get the value of my precedent row. I made a formula that says if I am in theoritical situation I want the theoritical value, and if I am in real situation I want the real value.
Thank you for your help anyway !
Corentin
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives