Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Planing a load of production
Hello
I'm trying to make sheet that I will be able to put orders, amount of planed hours on task and devide for different type of teams, employees.
I have stuck on one logic function. At the moment, when not all informations are typed in, function below returns blank cell.
=IF(ISERROR(PRORATE($[Total hours]32, $Start32, $Finish32, DATE(2017, [1]$2, [1]$4), DATE(2017, [1]$3, [1]$5))), "", PRORATE($[Total hours]32, $Start32, $Finish32, DATE(2017, [1]$2, [1]$4), DATE(2017, [1]$3, [1]$5)))
I would like to add to it also logic function, that will return blank cell if result of function is equal 0 (zero)
Do You have any idea?
Example of this sheet is available below.
https://app.smartsheet.com/b/publish?EQBCT=0d91ca8bc3bb4ae096bce2b0d4c3b280
Comments
-
That's quite a sheet you have there.
First, try changing your IF(ISERROR()) to IFERROR()
around your the whole function, add your if = 0
so
=IF ( IFERROR ( PRORATE(), "") = 0, "", PRORATE() )
I really don't like repeating the PRORATE() calc, but your sheet is already complicated enough without adding more columns. Because you have PRORATE throwing errors, you get into a vicious circle of trying to catch it.Hope that helps.
Craig
-
Thank You a lot.
This have solved my problem with displaying 0.
I have another question.
In Prorate function i need to use range of dates for calculation. In my case range is a calendar week.
Easiest way for me was to create by hand 4 rows that contain a month and day at beginning of a week and end of a week.
Row 2 contain month in first day of a week
Row 3 contain month in last day of a week
Row 4 contain day in first day of a week
Row 5 contain day in last day of a week
DATE(2017, [1]$2, [1]$4), DATE(2017, [1]$3, [1]$5)
Is there more simple solution for finding this range?
-
Do you need all of those columns for other reasons?
If so, the solution you have, while complicated on the surface, gets the job done.
Craig
-
Column 1 -52 represents a week number.
I did not find any other way to both have gant chart and table with amount of hours based on task --> team.
Basically I need it to get some forecast of load in workshop, to plan when I can take another order etc.
If there is no better way I will work with solution that i have.
Thank You for help
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives