How do you show the percentage time for a task being different across the period?
If someone is doing a task across multiple months, but is working 20% of their time in January, 30% of their time in February and 100% in March - how do you display this in Smartsheets?
Answers
-
First, you will need to have the data available regarding the % allocation for an individual across the time period you are measuring, in this case sounds like monthly. You could organize this into a resource Sheet.
In a project sheet that lists a task(s) over time, you could reference the resource sheet via a lookup formula to pull in the % allocation for the current month via something like a MONTH(TODAY())) formula, or you could create columns for each month and pull in static data per month.
School of Sheets (Smartsheet Partner)
If my answer helped please accept and react w/💡Insightful, ⬆️ Vote Up, ❤️Awesome!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives