Trigger after 30 days
I am trying to set up a trigger that will request an update after 30 days has past from the delivery date but using the not in the last (30) days request doesn't seem to work as it is requesting information from people to early. Any idea what trigger would activate 30 days after a date?
Best Answer
-
That trigger I think is "within the last 30 days", which would explain the issue you're having.
I think you're looking for "30 days after" the date field you're looking at. Screenshot below:
Answers
-
That trigger I think is "within the last 30 days", which would explain the issue you're having.
I think you're looking for "30 days after" the date field you're looking at. Screenshot below:
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives