Hope everyone is doing well? I'm looking for a formula or suggestions to accomplish the following:
IF “On schedule % Complete is > Actual % Complete then the task is “Late”, “Red Ball”.
IF “On schedule % Complete is < Actual % Complete then the task is “On track”, “Green Ball”.
IF “On schedule % Complete is = 0% (Actual % Complete) then the task is “Not Started”, “Grey Ball”.
Scenario:
Actual % Complete is currently being given based on progress from task owners. “On Schedule % Complete” is an automated value based on the task duration. For example, if I have a task that is 5 days long, each workday would be worth 20% complete, 100% at the end. However, if at end of 5 days the task owner reports 25%, then the task would be late. But we can also predict that the new end date will be 3 weeks/ 15 days from now based on the current reported progress.
Any information would be greatly appreciated,
Thank you.
Steve