Percent Complete not adding up

I need some help figuring out how to make my "% Complete" column reflect the actual percentage using my "Hours" column and not "SLA" (days). The sample below is clearly incorrect. It should be more like 64% complete.
I'm totally stumped.
Comments
-
Eric,
I may be incorrect, but I believe % Complete is derived based on days (not hours) and Duration; therefore, you need to have a DURATION column active on the sheet by enabling DEPENDENCIES.
Try enabling Duration if you haven't already done so (right click on any column heading, select "Edit Project Settings", click box to enable Dependencies).
I hope that solves it.
The other thing to note is that Duration completely impacts % Complete - I have a plan that has several 1 day tasks - when these tasks are marked 100% complete it does not impact the overall % complete unless other tasks with much lnger durations are already 100% complete. Does that make sense?
Keep us posted!
Suzanne
-
Eric,
If your SLA column is the Duration column renamed, then 19% appears to be correct.
There are 3 tasks under Phase I - Field Notification
1. General Information Bulletin (2d)
2. Smartsheet (1d)
3. Testing (13d)
The first two are complete, the last is at 0%
3d/16d= 18.75%
Smartsheet's % Complete rollup ignores Allocation %.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 206 Use Cases
- 517 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 83 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives