Percent Complete not adding up
Comments
-
Eric,
I may be incorrect, but I believe % Complete is derived based on days (not hours) and Duration; therefore, you need to have a DURATION column active on the sheet by enabling DEPENDENCIES.
Try enabling Duration if you haven't already done so (right click on any column heading, select "Edit Project Settings", click box to enable Dependencies).
I hope that solves it.
The other thing to note is that Duration completely impacts % Complete - I have a plan that has several 1 day tasks - when these tasks are marked 100% complete it does not impact the overall % complete unless other tasks with much lnger durations are already 100% complete. Does that make sense?
Keep us posted!
Suzanne
-
Eric,
If your SLA column is the Duration column renamed, then 19% appears to be correct.
There are 3 tasks under Phase I - Field Notification
1. General Information Bulletin (2d)
2. Smartsheet (1d)
3. Testing (13d)
The first two are complete, the last is at 0%
3d/16d= 18.75%
Smartsheet's % Complete rollup ignores Allocation %.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.4K Get Help
- 424 Global Discussions
- 221 Industry Talk
- 463 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 59 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives