Percent Complete not adding up
Comments
-
Eric,
I may be incorrect, but I believe % Complete is derived based on days (not hours) and Duration; therefore, you need to have a DURATION column active on the sheet by enabling DEPENDENCIES.
Try enabling Duration if you haven't already done so (right click on any column heading, select "Edit Project Settings", click box to enable Dependencies).
I hope that solves it.
The other thing to note is that Duration completely impacts % Complete - I have a plan that has several 1 day tasks - when these tasks are marked 100% complete it does not impact the overall % complete unless other tasks with much lnger durations are already 100% complete. Does that make sense?
Keep us posted!
Suzanne
-
Eric,
If your SLA column is the Duration column renamed, then 19% appears to be correct.
There are 3 tasks under Phase I - Field Notification
1. General Information Bulletin (2d)
2. Smartsheet (1d)
3. Testing (13d)
The first two are complete, the last is at 0%
3d/16d= 18.75%
Smartsheet's % Complete rollup ignores Allocation %.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives