Duration not correct
Hi I am doing a project that commences on 14th May 2018 as is suppose to have a duration of 12 weeks (84days).
84 days should end on 3rd August 2018, but 84 days is calculated to end by smartsheet on September 6th 2018?
Why is it showing as this and what can I do to fix it.
Thanks
Best Answer
-
@Mia Ryan , it is using weekdays. You should be able to go into your Project Settings and edit your "Working Days" and add in the missing Saturdays and Sundays.
Answers
-
@Mia Ryan , it is using weekdays. You should be able to go into your Project Settings and edit your "Working Days" and add in the missing Saturdays and Sundays.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 371 Global Discussions
- 205 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 448 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives