Hi All,
I have project plan sheets set up for my project managers to use. each project has 4 phases which have parent rows set up to catch up each phases progress along with a top line project row that captures overall project progress.
I have created programme reports that look at these sheets to show a project by project progress for senior management to review.
What I would like to do is have a top line programme row that rolls up the individual project dates to give an overall programme start/finish progress % etc?
Is this possible within the report functionality on Smartsheets to add a top programme line or am I going to need to build it on a grid with links to cells on the other sheets?
Attached is the report I have made pulling the projects together, it is the top row pulling it all together for programme detail that I am missing.
Thanks,
Greg Peddell-Grant