I would like to create a report that shows all tasks assigned to an individual across all projects. This is pretty simple for current workspaces, but I don't know of a way to have new workspaces automatically added to the report.
Currently each project is set up as a new workspace, and someone like a department head could be shared and have tasks on 10+ projects, and new projects could be added every couple weeks. Does anyone know of a good workaround that would show all tasks assigned to someone without the risk of a project falling through the cracks because someone forgot to manually add the new workspace to the report?
Best Answer
-
Using Control Center you can use the meta data that you set to create Roll-up reports. Otherwise, reports do not inherently add new sheets as they are created.
Answers
-
Does Control Center have functionality that makes this possible?
-
Using Control Center you can use the meta data that you set to create Roll-up reports. Otherwise, reports do not inherently add new sheets as they are created.
Categories
- All Categories
- 14 Welcome to the Community
- 10.8K Get Help
- 65 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives