Defining Resource wise nonworking days
I have been exploring the smartsheet and so far it looks okay. But I could not find one major feature here which is (should be) present in any other project management tool. I was looking for the option for defining Resource wise nonworking days but was unable to find it. e.g. John is a resource in my project and he will take the personal time off (casual leave) on 11/18/2020 and 11/23/2020. I want to give entry of these personal time off somewhere in the smart sheet so that during scheduling these will be excluded. Can you please let me know how to achieve this in the smartsheet?
For better understanding here I am attaching a screenshot from MS Project where I can manage resource-wise personal time off.
Answers
-
Currently working days & non-working in Smartsheet are set on a per-project basis, in the Project Settings for each sheet, versus being based on each individual resource/person.
You may want to look at 10,000ft (see here) as a Resource Management platform as an alternate way of tracking working days and resources. You could then use the 10,000ft Panel in Smartsheet to connect the two platforms together.
I hope this helps!
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.3K Get Help
- 462 Global Discussions
- 156 Industry Talk
- 506 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 517 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives