Gantt - Adjusting through mobile app
Hi,
I am a contractor and utilize my project gantt charts in the field quite often. When a task is running late by a few days, I adjust the days of the task there in the field. Recently, I had vendor tell me he would be arriving on a specific day, so I need to unlock the dynamic piece of his task and set it to that day, so it does not adjust based on anything else.
I can't find a way to do this in the app. Any suggestions?
Answers
-
Hi,
Start and end dates becomes cells with formulas the moment you enable dependencies in the project settings. Any cells which have formulas are not editable through the native mobile app. That is a limitation currently. As an interim solution, you can access Smartsheet through the browser to edit the end date
Thanks,
Aravind
Associate Director
Copernicus Consulting Pte. Ltd.
P: +65 9230 5657 | E: aravind@copernicusworld.com
Feel free to reach out for licenses, services, and training on Smartsheet
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives