Gantt - Adjusting through mobile app

Hi,

I am a contractor and utilize my project gantt charts in the field quite often. When a task is running late by a few days, I adjust the days of the task there in the field. Recently, I had vendor tell me he would be arriving on a specific day, so I need to unlock the dynamic piece of his task and set it to that day, so it does not adjust based on anything else.

I can't find a way to do this in the app. Any suggestions?

Answers

  • Aravind GP
    Aravind GP ✭✭✭

    Hi,


    Start and end dates becomes cells with formulas the moment you enable dependencies in the project settings. Any cells which have formulas are not editable through the native mobile app. That is a limitation currently. As an interim solution, you can access Smartsheet through the browser to edit the end date

    Thanks,

    Aravind

    Associate Director

    Copernicus Consulting Pte. Ltd.

    P: +65 9230 5657 | E: aravind@copernicusworld.com

    Feel free to reach out for licenses, services, and training on Smartsheet