Can anyone recommend the best formula to calculate overdue tasks?
Currently using- =COUNTIFS(AND({SS Project Plan Completion Date Range}, NOT([{SS Project Plan Status Range} = "Complete")]) < TODAY())
I want to exclude completed task from the count. Currently returning UNPARSEABLE error
Tags:
Answers
-
Hey
Perhaps it might be because your first Logic Expression after AND is incomplete. What should the {SS Project Plan Completion Date Range} be?
Hope it helps,
Regards,
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!