How do I assign a resource group as project activities?

FernandesBR
FernandesBR ✭✭
edited 11/23/20 in Smartsheet Basics


For example: I have a factory with 100 people, which has a capacity of 600 hours per day (6 hours / person x 100 people). I do not need to allocate each person, but only the total capacity. In the resource panel I can get a maximum of 24 hours.

Is there a way to define a capacity for each resource individually?

Does anyone know any alternative or way to work with group allocation?


Answers

  • Stefan
    Stefan ✭✭✭✭✭✭

    Hi @FernandesBR,

    within Smartsheet allocation and % of utilisation is centered around persons as resources and thus 24h per day is the maximum.

    Without knowing about your process and what role this factory resource plays, maybe 10.000ft by Smartsheet can help here? At least you can individual capacities there.

    Hope this is of some help

    Stefan

    Smartsheet Consulting, Solution Building, Training and Support.

    Projects for Processes and for People.