Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Schedule Duration Issues
I've been working in a CPM schedule. The original showed a 141 day duration, starting 12/12 and ending 05/04. I'm updating some of the relationships as I had to rearrange the work pattern a bit, now my schedule shows 144 days, starting 12/12 and ending 6/29. Does anyone have an answer as to how I gained only 3 days duration yet two full months were tacked onto my end date? I have a feeling it's the way Smartsheet defines duration... but I would thing duration is linked to the days between the start and end of a project.
Insight would be appreciated.
Comments
-
Cancel that, Ghost-Rider. Solution acheived. I've obviously been staring at this too long.
-
can you advise your solution?
Did smart sheet ever reflect changes to correponding activities jus as Microsoft project would do?
-
Maggie -
It wasn't an issue of Smartsheet malfunctioning. It's working just as intended. It was an issue of myself comparing two schedules end dates that I had failed to update the starting date on... like, duh. So obviously my end date was going to be two months out when I didn't update the start date to be the actual start date.... It was a facepalm moment.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives