I want the date field to include date and time

The created field has a default date and time. How do I get this to my user field? I want both date and time in one cell to allow duration calculations...

Best Answers

  • ✭✭✭✭✭✭
    Answer ✓

    Hi @Robert Gallegos

    Hope you are fine, please try the following formula:

    =LEFT(Created@row, 18)

    PMP Certified

    bassam.khalil2009@gmail.com

    ☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"

  • Community Champion
    Answer ✓

    Hi @Robert Gallegos

    To add to Bassam's excellent advice/answer.

    Please have a look at my post below with a method I developed.

    More info: 

    Lock or Store Date/Value Solution without using Zapier


    Would that work/help?

    I hope that helps!

    Be safe and have a fantastic week!

    Best,

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

Answers

  • ✭✭✭✭✭✭
    Answer ✓

    Hi @Robert Gallegos

    Hope you are fine, please try the following formula:

    =LEFT(Created@row, 18)

    PMP Certified

    bassam.khalil2009@gmail.com

    ☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"

  • Bassam, Excellent work around. Any suggestions to trigger another date (finish date) like the created date?

  • Community Champion
    Answer ✓

    Hi @Robert Gallegos

    To add to Bassam's excellent advice/answer.

    Please have a look at my post below with a method I developed.

    More info: 

    Lock or Store Date/Value Solution without using Zapier


    Would that work/help?

    I hope that helps!

    Be safe and have a fantastic week!

    Best,

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

  • ✭✭✭✭✭✭

    At your service anytime @Robert Gallegos

    and please check the great information in @Andrée Starå post

    PMP Certified

    bassam.khalil2009@gmail.com

    ☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"

Trending in Smartsheet Basics