%Complete Issue
An editor of a project schedule sheet that I created is having issues with %Complete field. When he enters a number, it is multiplied by 100. So, when he updates %Complete to 50, the field shows 5,000% instead of 50%. As owner of the sheet, I am not having the same issue. Any ideas how it can be fixed?
Answers
-
Not sure why it would be different for a sheet editor as compared to the owner, but I believe you need to enter the %Complete as a decimal, for example 0.5 for 50%, 1 for 100%, or 0.75 for 75%.