%Complete Issue

An editor of a project schedule sheet that I created is having issues with %Complete field. When he enters a number, it is multiplied by 100. So, when he updates %Complete to 50, the field shows 5,000% instead of 50%. As owner of the sheet, I am not having the same issue. Any ideas how it can be fixed?


Answers