Calendar View
When using Calendar View, is there a way for it to display the start and finish date range instead of a single date on the calendar? If so, how do I do that?
Best Answer
-
Hi Becca,
You should be able to do it by going into your project settings and selecting start/end dates. To do so, right click on any column header and select "Edit Project Settings."
From there, you can select which column is your start date and which is your end date.
Hope this helps!
Best,
Heather
Answers
-
Hi Becca,
You should be able to do it by going into your project settings and selecting start/end dates. To do so, right click on any column header and select "Edit Project Settings."
From there, you can select which column is your start date and which is your end date.
Hope this helps!
Best,
Heather
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.5K Get Help
- 367 Global Discussions
- 202 Industry Talk
- 432 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 447 Show & Tell
- 29 Member Spotlight
- 1 SmartStories
- 285 Events
- 36 Webinars
- 7.3K Forum Archives