Hello
I have been trying to nail this down for the past couple of weeks but falling short. I need a column that shows Red, Green, or Yellow based on Actual % Complete vs Projected % Complete. I am calling it Progress Alert. I need it to show the following:
If Actual % Complete is 25%+ behind Projected % Complete show Red
If Actual % Complete is 15%+ behind Projected % Complete show Yellow
If Actual % Complete is 10% or less behind Projected % show Green
If Actual % Complete is ahead of Projected % at all show Green
Background- I currently have the Progress Alert working with the Progress column Harvey balls but the last criteria listed above doesn't work. If the Progress is ahead of Projected % Complete the Progress Alert is showing Red which is our main issue. I added an Actual % Complete which converts the Harvey balls to % hoping that may make it easier to do the formula. The Projected Complete is calculated based on the days on the Planned Dates.
Any help would be much appreciated!