Smartsheet Calendar
Hello,
I am wondering if the Smarsheet calendar has the capability to move an entire employees daily work to the next day. For instance, if an employee has a rain day and needs their entire schedule moved by one day can you set it up to do it manually by just moving the first day?
Thank you,
Answers
-
If you set up Project Settings in your sheet and enable dependencies, this would configure your sheet to have dates dependent on each other (where a date would move if a previous date changed).
However Project Settings will link a Start and End date to a Duration of a task as well, and this setting is mainly used in conjunction with a Gantt chart, not the Calendar View. See this article for more information on Gantt charts: Gantt Chart with Dependencies. You may also want to read this article as well: Enable Dependencies and Use Predecessors.
If you are simply using one column for your dates and the Calendar view, then there isn't a way to automatically shift all your following dates based on this one adjustment. You could use the drag-fill function in Grid view to quickly input a series of dates in a specific pattern. See: Create a Series of Numbers or Dates with Drag-Fill.
Let me know if I've misunderstood your question or if I can clarify anything further!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives