Calculating Difference Between Multiple Dates
Hello,
Curious if there's a single formula to calculate difference between Planned and Actual for both start date and end date? Trying to get the Total Time +/- value.
Thanks.
Answers
-
Hi-
Have you tried either the NETWORKDAYS or NETDAYS formula? NETWORKDAYS will give you the # of work days between the 2 and NETDAYS will give you the # of days between the 2 (including non-working days). The column where you are entering the formula should not be a date field.
Hope this helps!
Amy
-
Hi Amy,
Yes, the column for the formula isn't a date field plus the NETWORKDAYS &/or NETDAYS works but only for calculating 2 dates (Planned Start - Actual Start).
My aim is a formula (using any available) that can calculate the total of all 4 dates.
Ex. = (Planned Start - Actual Start) + (Planned Finish - Actual Finish)
I've tried a variety of ways to write it but keep coming up with errors.
Thanks!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives