Link Dependency Lead/Lag Times to a cell value?
Is there a way to link a row's dependencies' lead/lag time to a calculated value? The only way I see to change that value is by editing the dependency directly. It would be helpful to be able to calculate what the lead or lag is based on a number of factors. Is that possible?
Best Answer
-
No, currently in Smartsheet the lead/lag time will need to be adjusted manually by editing the dependency directly, as you've found. Please let the Product team know about your use-case and feature request by filling in this form, here!
Thank you,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
No, currently in Smartsheet the lead/lag time will need to be adjusted manually by editing the dependency directly, as you've found. Please let the Product team know about your use-case and feature request by filling in this form, here!
Thank you,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.7K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives