Link Dependency Lead/Lag Times to a cell value?
Is there a way to link a row's dependencies' lead/lag time to a calculated value? The only way I see to change that value is by editing the dependency directly. It would be helpful to be able to calculate what the lead or lag is based on a number of factors. Is that possible?
Best Answer
-
No, currently in Smartsheet the lead/lag time will need to be adjusted manually by editing the dependency directly, as you've found. Please let the Product team know about your use-case and feature request by filling in this form, here!
Thank you,
Genevieve
Answers
-
No, currently in Smartsheet the lead/lag time will need to be adjusted manually by editing the dependency directly, as you've found. Please let the Product team know about your use-case and feature request by filling in this form, here!
Thank you,
Genevieve
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 68 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives