Schedule Health formula not working,
Hi,
Can anyone help me with a formula i have three scenario
.1 & 2. IF start date and end date % complete activity exceed the daily % completion , Status should be In progress and color the schedule health to Green
3 % complete is less than the expected work to be completed within the time frame it should be Red and status should be In progress
Answers
-
Good morning,
Try this for your schedule health:
=IF((NETWORKDAY([Start date]@row, today())/NETWORKDAY([start date]@row, [end date]@row))<[% complete]@row, "Red", "Green")
Work?
Mark
I'm grateful for your "Vote Up" or "Insightful". Thank you for contributing to the Community.
-
Hi @Mark Cronk
I think something is not correct on the formula as you could see % complete is more than 50% and start date has not yet came so this should be green not red.
-
What formula are you using in your %complete column that's marking a takes complete when it hasn't started?
Try this to correct you status issue:
=IF(AND(ISDATE([start date]@row), [start date]@row<today()), IF((NETWORKDAY([Start date]@row, today())/NETWORKDAY([start date]@row, [end date]@row))<[% complete]@row, "Red", "Green"))
Getting closer?
Mark
I'm grateful for your "Vote Up" or "Insightful". Thank you for contributing to the Community.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!