Is there a way to track due date changes besides looking at the activity log?
We have a Professional Service Agreement that identifies clear dates/deliverables. Some of those have been adjusted by agreement. I'd like a timeline that indicates the date of adjustment & action taken, and then the new timeline/deliverable. Conversely, an "Original Date" of deliverables should be called out on timeline.
Suggestions on the best way to achieve this type of tracking with Smartsheet?
Answers
-
Hi @Sara Ross
I hope you're well and safe!
One possible method could be to use the Baseline feature.
Can you describe your process in more detail and maybe share the sheet(s)/copies of the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
Would that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.1K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 444 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 450 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 290 Events
- 35 Webinars
- 7.3K Forum Archives