Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Estimated vs Actual Time

How does everyone accurately document their Estimated Time vs Actual Time Spent on tasks for a project?
Currently, in our planning process we assign a Start Date and an End Date for each task (with allocation %, duration, and predecessors for each task) once the person assigned to the task acknowledges and begins working, they update their % complete until task is complete. We know when the task is 100% complete but when we look back at the project we cant see if they actually finished the task in 1 day when we estimated 2, etc.
How do you all keep up with this without the person assigned to a task manually changing start date, end date, allocation %, duration?
Comments
-
Add 3-4 additional columns:
Baseline Start Date, Baseline End Date, Baseline Variances (make 2 columns if you need to check variances to both start and end dates)
How to use this:
Fill out all your start/end dates with what you are projecting. Copy these dates over to your baseline date columns. When you actually work on the project, adjust the start/end dates as needed. The Baseline variance formula should subtract the difference between a baseline start date, and the actual start date. So you can essentially see if you start date is +/- 3 days from when you projected.
Clear as mud?
-
Hi Brent,
That's a nice idea that you have suggested. The only downside that i see, is that, if the resource takes an unplanned PTO (currently,one cannot mark non-working day for an individual resource), the only option is to increase the duration and put a note that he/she is on PTO. This would cause an "improper" data when calculating the actual effort as you suggested. How do you handle this in your plan?
Robert
-
Break the task down into child tasks.
- Start/End Dates- part 1
- Gap in dates for leave of absence
- Task 2 date range.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.2K Get Help
- 431 Global Discussions
- 152 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 74 Community Job Board
- 501 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 306 Events
- 36 Webinars
- 7.3K Forum Archives