filtering tasks taking place in a specific calendar week
Hi,
I've created production plan which is used by different departments for planning, checking, production capacity calculation's.
I would like to create a filter which shows all tasks taking plate in specific calendar week.
For exaple:
I know that in week 44 I will have overbooking on production capacity, if I won't reschedule some of the tasks.
I would like to have a possibility to filter all those tasks in specific week, which going to start/finish/or continue in specific calendar week.
Thank You in advance for any help from Your side.
Best Answer
-
Could you please share me as an admin on a copy of your sheet after removing any sensitive data so I can solve this problem for you.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Answers
-
Hi @Piotr Górczewski
Hope you are fine, you can do that by adding a helper column call it week number and use the following formula to calculate for each task:
=WEEKNUMBER(Date@row)
then you can create a report filtered by Department & overbooking on production capacity and group that report using Week number. the following screenshot shows a sample
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Hi @Bassam Khalil,
Thank You for the hint about "WEEKNUMBER" formula.
I will have to look deper in to the potential of this solution.
Here You have an example of my schedule.
I've added "Week" column but i don't know how to write the formula which will calculate in which weeks "STEP" column Starts + have a duration and than Ends.
I'm wondering if there is any option to write this formula to show all the weeks in which each STEP exists.
-
Could you please share me as an admin on a copy of your sheet after removing any sensitive data so I can solve this problem for you.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
-
Sorry for delay, i add to column for you with the a WEEKNUMBER formula for Planned start & Planned Finish check it please.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Hi @Bassam Khalil ,
Thank You for Your effort.
Ho to filter al those "STEPS" from my schedule which are ongoing e.g in week 18?
For example:
STEP Assembly/Welding starts in week 17 and ends in week 25.
How to set a filter to see that row for all STEPS taking place in week 18?
I hope you understand my twisted explanation 😁
-
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives