Colored Gantt Charts on Dashboard

Hello,


I colorized my milestone Gantt chart in my project plan, but the colors don't carry over to the report or the dashboard. Does anyone have any ideas on how to solution this?

Answers

  • Hi @Kayla Smith

    Another Community member had a similar issue; in their case, logging out of Smartsheet then logging in again brought the coloured rows through from the source sheet to the Report and Dashboard. Could you try this?

    If this doesn't resolve your issue, can you post some screen captures of what you're seeing (but please block out any sensitive data). It would be helpful to know what browser you're using and how you coloured the rows (conditional formatting or manual?)

    Cheers,

    Genevieve

    Need more help? 👀 | Help and Learning Center

    こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions