Date duration subtraction
Not sure how to explain this. I have attached a photo of how its done in Excel and the actual smartsheet.
I have a migration state date of July 28th and several tasks after. I need the cell in start time to change if I decrease or increase the lead time. I cant figure out any formula or if its even possible.
Excel Example
Smartsheet
Answers
-
Hey @Zane Fielding,
It looks like you are trying to subtract a date from a number and return the resulting date. I have created an example below on how this formula may look like:
- Formula: =$[Migration Start Date]$1 - [Lead Time]@row
Take note that the "$" signs are used to create Absolute References.
I hope this helps!
Jaykel
-
@Jaykel Torres I am actually trying to subtract a number from a date and return the resulting date.
-
@Jaykel Torres I tried the above formula and got a #INVALID OPERATION
-
Were you able to find a resolution to your question or are you still working on this?
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives