Multiple dependencies

Daniel Kumar
Daniel Kumar ✭✭✭
edited 10/06/21 in Formulas and Functions

Hi,

I have an issue that I'm not able to solve:

In this example I tried to define the beginning and the end of task 3 to be dependent on task 1 and task 2, respectively.

I want Task 3 to start when task 1 starts, and for the end of the event “finish-finish” with task 2.

As you can see, it automatically sets the correct end date. But the duration is set to 1d and does not start at the correct start date.

I want it to look like this:

So if task 1 or 2 have any changes, this will affect the duration of task 3).


Thanks!

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!