When setting an automation, does the "x" number of days include the actual Finish Date
For example, if I have a Finish date of 10-29-21 and set up an automation that will send a reminder when the Finish date is in the next (days) - ..does it count 10-29-21 as one of those days?
In other words, will my reminder go out on the actual Finish Date in this situation?
Thank you
Best Answer
-
Hey @Steve Patton,
When you set your Condition to "Where" the Date "is in the next (Days)", this Counts future days and not Today's Date. In example, if you were to set "is in the next (Days)" equal to 1, the Condition will be met one day before the "Where" date.
You can set your Condition to "Where" the Date "is Today" if you would like the condition to be met on Today's Date.
I hope this is clarifying!
Jaykel
Answers
-
Hey @Steve Patton,
When you set your Condition to "Where" the Date "is in the next (Days)", this Counts future days and not Today's Date. In example, if you were to set "is in the next (Days)" equal to 1, the Condition will be met one day before the "Where" date.
You can set your Condition to "Where" the Date "is Today" if you would like the condition to be met on Today's Date.
I hope this is clarifying!
Jaykel
-
Thank you...this answers my question!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives