Task spanning multiple sprints

Kerri S
Kerri S ✭✭
edited 06/14/22 in Add Ons and Integrations

Hello,

I am using the Jira to Smartsheet connector to pull Issues into a Smartsheet. I have tasks and stories that span multiple sprints in scenarios when it is not completed in the original sprint. Jira's Sprint Report shows all the sprints that the story or task was assigned to. The Jira to Smartsheet connector is only pulling the sprint where the story or task was completed. This results in not being able to represent a story or task that was assigned to a sprint, but not completed in that sprint. Thanks for your support!

Best Answer

Answers