change cell value based on a predecessor row
HI. Is it possible to change a cell value based on a change in another row? The sheet i am working in has a column for task status (Normal, Critical, Complete, Waiting on Contingency). Some rows have predecessors. A row with a predecessor has a Task Status of "waiting on contingency" if it has a predecessor row. Is it possible to change this task status to "Normal" once the predecessor row task status changes to "complete"? There are very few actual dates in this sheet. All the dates are relative.
Perhaps there is even a better way to handle this situation.
TIA!
Answers
-
Hi @Karen Ferency
Hope you are fine, yes you can use change cell Value workflow to do that.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
@Bassam Khalil That would not work as we need to be able to reference the predecessor on each row.
@Karen Ferency Here is a link to a thread that explores the new SUCCESSORS function. I am sure we should be able to adapt the solution outlined in the original post there.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives