Want to Calculate the Number of days a task is in OPEN status
When the status changes from Open to In-progress the calculation gets reset to 0 days, Please Guide Thanks!
Best Answer
-
How are you currently doing your calculations?
It sounds like you could set up two helper Date columns in your sheet:
- One column will automatically record the Date that a row's status changes to "Open"
- A second column will automatically record the Date when the status changes to any other Status
See: Set the Current Date with Record a Date Action
Then you can set up a formula to count the days between those two date stamps. Let me know if this will work for you!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
How are you currently doing your calculations?
It sounds like you could set up two helper Date columns in your sheet:
- One column will automatically record the Date that a row's status changes to "Open"
- A second column will automatically record the Date when the status changes to any other Status
See: Set the Current Date with Record a Date Action
Then you can set up a formula to count the days between those two date stamps. Let me know if this will work for you!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 396 Global Discussions
- 213 Industry Talk
- 448 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 133 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!