testing a website: tracking user acceptance testing in a sheet
Hello,
I'd like to use sheets to track user acceptance testing. That is, there is a task/item and then the user looks at the task and says it passes or needs remediation. My question is how to do I create a useful dashboard when there is no completed task %? Each user gets their own testing sheet. I can create reports based on passing status but how do I rollup which users still have the rows to complete or which users are done? We aren't using any dates or milestones either.
Thanks.
Janet
Best Answer
-
It sounds like a Report is the way to go! You can use a Report to bring together multiple sheets. Then you can Group by the user (or the sheet, if that has the user name), and then you can do a second Group based on Status (ex. "Complete" or not).
Once you have the two Groupings, you can add a Summary to COUNT how many rows are in each status, per user/sheet.
Here's a webinar that you may find useful: Redesigned Reports with Grouping and Summary Functions
If this doesn't help, would you be able to post a screen capture of what the sheet structure looks like?
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
It sounds like a Report is the way to go! You can use a Report to bring together multiple sheets. Then you can Group by the user (or the sheet, if that has the user name), and then you can do a second Group based on Status (ex. "Complete" or not).
Once you have the two Groupings, you can add a Summary to COUNT how many rows are in each status, per user/sheet.
Here's a webinar that you may find useful: Redesigned Reports with Grouping and Summary Functions
If this doesn't help, would you be able to post a screen capture of what the sheet structure looks like?
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Thanks! I was able to do a rollup sheet with percentage of completed items shown (pulling from each sheet). Then pull that rollup sheet into the dashboard. The dashboard is a little more automated that way. I also was able to do a countif if the completed items was 100% and signed off and pull that number into the dashboard for a high level, dynamically updated overview. Thanks again for your response!
Janet
-
Hi Janet.
I'm glad you were able to figure this out with formulas, well-done!
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives