Hello! I originally created my plan using to have start date then to add in the start and end times. I was using this formula: =StartDate@row + duration@row + "". However, I just realized that my project will be operating under two sets of working times: 8 hours to start then pivoting to 24 hour days. Since smartsheet only allows for one set of working times, I need to adjust the start times for the first set of tasks so they start at 8 am instead of midnight. I tried adjusting the formula to the following: =StartDate@row + duration@row + adjustment@row but what happens is the following: 12/3/21 8:00 AM8h. It's not adjusting the time, just adding the text in the Adjustment field.
Is there a way to adjust the formula so that it will add in both the duration and adjustment? If not, is there an alternative method that I could try? I asked a colleague and their only suggestion was to reset all my dependencies to the Adjustment field but that seems too time consuming since my plan is 4k+ lines.
Any help would be greatly appreciated!