We use "Baseline", "Planned" and "Actual" Start & Finish columns on our projects.
Is there a way to automatically update "Planned" dates for successor activities based on the "Actual" dates for predecessor activities?
e.g. If a predecessor's "Actual Finish" occurs 2 days earlier than its "Planned Finish", can Smartsheet pull "Planned Start" and "Planned Finish" dates for successor activities by 2 days?