Multiple dates/colors in Gantt View
So I have multiple dates, overall project dates and backend development dates which fall inside the overall project dates. Can I have one bad but it be a different color to signify the backend development date within the overall project bar?
Answers
-
You can set up custom colours in your Gantt chart either by manually changing the colour of the bar or by setting a Conditional Formatting rule. See: Change the Color of Task Bars
To manually change the colour, you can right-click on the bar you want to adjust and select Color Settings:
In Conditional Formatting rules, you'll want the rule to be set for the entire row, then change the Task Bar colour portion:
See: Apply Formatting Automatically with Conditional Formatting Rules
Keep in mind that if you're using Hierarchy in your project, you will only be able to change the colour of Child Row tasks. See the Note in the bottom of this Help Article: Parent Rollup Functionality
Parent Rows will always display as a grey bar showing the earliest start and the latest end date of their Child tasks:
If I've misunderstood your question it would be helpful to see screen captures of your sheet set-up, but please block out sensitive data.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65K Get Help
- 443 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 129 Brandfolder
- 150 Just for fun
- 70 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives