Dashboard/Report to show status change in last 30 days

Rick_Bailey
Rick_Bailey ✭✭✭✭✭
edited 02/09/22 in Smartsheet Basics

Hi, I'm looking to be able to show on a dashboard a chart and detail of projects that have had a status change (RYG) in a given period of time (last 30 days). It doesn't appear that reports allows to filter on that type of data. any suggestions?

Thanks!

UPDATE- solved via Automated work flow using an added date column, and then building a report filtering said column if blank.