Dashboard/Report to show status change in last 30 days

Rick_Bailey
✭✭✭✭✭
Hi, I'm looking to be able to show on a dashboard a chart and detail of projects that have had a status change (RYG) in a given period of time (last 30 days). It doesn't appear that reports allows to filter on that type of data. any suggestions?
Thanks!
UPDATE- solved via Automated work flow using an added date column, and then building a report filtering said column if blank.
Tags:
Answers
-
Hi @Rick_Bailey
Thanks for sharing your solution! Using the Record a Date workflow was a great way to gather this type of data.
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.9K Get Help
- 429 Global Discussions
- 147 Industry Talk
- 487 Announcements
- 5.2K Ideas & Feature Requests
- 86 Brandfolder
- 151 Just for fun
- 74 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives