Activity Completion / Critical Path -
Hello everyone,
I have a very basic question, but the solution doesn't seem to present itself to me directly.
Question - How do you best signify that an activity is completed within your sheet? Is there a way to minimize the bar shown in the Gantt chart without labeling a duration as 0?
Currently, I have conditional formatting applied (Not Started - Red, In Progress - Yellow, & Completed - Green) that highlights rows to emphasize their current status. I do have a % Complete column as well, but have not linked any formatting to that column.
Recently, I added a critical path filter to isolate tasks associated with the critical path.
My problem is that even after activities are completed, the red critical bath bar is still observed (the row is just highlighted in green). See attached picture below, green = completed activity but the red critical path bar is still displayed.
If I change the duration to 0 (like a milestone), my project dates will all adjust and not reflect the current state.
How do other users signify tasks have been completed? Is there a way avoid having completed tasks populate on the Gantt chart's critical path / critical path filter?
Note - I apologize that my questions isn't articulated well / concise. Having a difficult time conveying my situation appropriately.
Thank you,
Jordan
Answers
-
The critical path is the critical path regardless of % Complete.
You could use conditional formatting to change to color of the bar within the Gantt chart though. You can either have it change color based on status so that it is visible but obvious that it is completed, or you can change it to match the cell fill. It will still be somewhat visible, but it won't stand out quite as much.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives