Partially missing resources after connecting sheet to Resource Management
I have entered my resources in Resource Management, but after connecting to a project, not all of my resources are populating in the sheet. I have a "talent pool" situation at the top of my sheet with dates and 1% allocated. Most of my resources are populating, but not all, even after being assigned to a task. Any thoughts?
Answers
-
Hi @Amy F
Are all of your resources Members of your Smartsheet plan? They can be unlicensed/free users, but they would need to be associated with your Smartsheet organization to be matched up with the email address that's used in Resource Management.
See: Admin Center: Add, Edit, and Delete Individual Users with User Management
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now -
@Genevieve P. Many thanks!! That was the issue.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 441 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 301 Events
- 33 Webinars
- 7.3K Forum Archives