Partially missing resources after connecting sheet to Resource Management

I have entered my resources in Resource Management, but after connecting to a project, not all of my resources are populating in the sheet. I have a "talent pool" situation at the top of my sheet with dates and 1% allocated. Most of my resources are populating, but not all, even after being assigned to a task. Any thoughts?
Answers
-
Hi @Amy F
Are all of your resources Members of your Smartsheet plan? They can be unlicensed/free users, but they would need to be associated with your Smartsheet organization to be matched up with the email address that's used in Resource Management.
See: Admin Center: Add, Edit, and Delete Individual Users with User Management
Cheers,
Genevieve
Need more information? π | Help and Learning Center
γγγ«γ‘γ― (Konnichiwa), Hallo, Hola, Bonjour, OlΓ‘, Ciao!π | Global Discussions
-
@Genevieve P. Many thanks!! That was the issue.