Can not create a link between end dates in the Smartsheet
Hello!
I am trying to create link between two regular Smartsheet's with dependencies enabled.
I can link start date to the "summary" Smartsheet, but when goes to the end date I am getting warning message. I found one response to similar issue, but didn't get that.
Best Answer
-
Unfortunately that is a limitation when dependencies are enabled :-(
Answers
-
Unfortunately that is a limitation when dependencies are enabled :-(