Creating a Milestone Sheet (referencing project plan)
Hi All,
I have created a project plan in Smartsheets and am tracking milestones using tags
How do I create a separate sheet which only shows me milestones, its start/finish (i.e start=earliest start date with a particular tag, and end=latest end date with a particular tag), its % completion (based on the milestone tag) and its health.
For example, I use tags milestone1, milestone2, milestone3 etc. against my main project plan and the new spreadsheet shows me the following
Tag: %Completion Start Finish
Milestone1 95% 3/1/22. 6/1/22
Milestone2 60% 3/15/22. 8/1/22
Answers
-
I would suggest creating a report that is filtered based on the tag containing "milestone".
-
Thank you Paul,
Smartsheet team helped me achieved this by creating a metric report and using formulae to capture earliest start date for a given milestone tag and latest end date for a given milestone tag.
Vin
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!