Task Scheduling
I am testing Smarsheet. I am satisfied with the task dependency support but noticed one thing I am not liking and that is - if I, for example, enter 4 tasks and add the dependencies causing the dates to adjust accordingly -- then remove a dependency on a task that got pushed out, it will not auto schedule itself back to project start date. In order to do this you would need a known project start date and an auto schedule feature (like ms project).
What can you tell me that would make me feel better about this? thanks.
Answers
-
You could set an additional dependency that refers back to the row containing the original project start date and set it as "SS".
-
@Paul Newcome Having to do that compels me to stay w/MS Project. I want tasks to auto schedule to project start date if they do not have a dependency w/o needed intervention.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 140 Just for fun
- 57 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives