Hi
I have a Jira connection set-up and have checked on the option to include the issue hierarchy. The connection is working and has populated my smartsheet. The hierarchy is working between stories, spikes & tasks & sub-tasks. But it is not working between features & stories, nor between epics & features.
Is this a smartsheet issue or could this be because of the way jira is configured? How does Smartsheet know that a feature is the parent of a story? What should I be looking for in Jira?
Thanks
Best Answer
-
Hi @Anthea
The JIRA Connector does not currently support custom hierarchies above epic level that are created using Portfolio or Advanced Roadmaps Jira add ons (such as Initiative, Program and Feature Porfolio fields).
Please provide your feedback to the Product team through this form, here.
Thanks,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Hi @Anthea
The JIRA Connector does not currently support custom hierarchies above epic level that are created using Portfolio or Advanced Roadmaps Jira add ons (such as Initiative, Program and Feature Porfolio fields).
Please provide your feedback to the Product team through this form, here.
Thanks,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 59 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives