Hard constrain the dates of a task
Hi all,
We use the dependencies to determine the timings of most of our tasks. Some of the tasks need to have dates which are hard constrained (ex: missions at / for customers, holidays...) with the other tasks adapting to the hard constrained tasks. Is that possible?
Very kind regards,
Antoine.
Answers
-
Hi @arennuit
There currently isn't a way in Smartsheet to both have a Predecessor set and have a hard constrained date. If you don't have a Predecessor for that row, then you can set a date and it won't change as you change the other tasks (and you can have dependent tasks still on this row, if needed). See: Enable Dependencies and Use Predecessors
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 140 Just for fun
- 57 Community Job Board
- 461 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives