Hello, I have a checkbox in a column named "Completed"
I'd like to have a formula that adds the number "100" to a column named "% Complete" if the box is checked.
I've read other posts and cannot get this to work. thanks!
Hi @chlod24
I hope you're well and safe!
I'd recommend using a combination of a Workflow and the Change Cell Action.
Would that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
@chlod24
Excellent!
Happy to help!
It usually takes between a few to 30 seconds for it to update. Try refreshing the sheet.
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
Hi thank you, yes I think this could work. I just tried it but it doesn't seem to trigger. Should it be instant? Thats what I'm looking for.
ref must be one of: categoryID, siteSectionID, category, category/categoryID, category/name, category/description, category/url, category/allowedDiscussionTypes, locale, siteSection, siteSection/basePath, siteSection/contentLocale, siteSection/sectionGroup, siteSection/sectionID, siteSection/name, siteSection/description, siteSection/apps, siteSection/attributes, layoutViewType, discussionID, commentID, page, sort, discussion, discussion/name, tags, breadcrumbs, discussionApiParams, serverDraftID, serverDraft.