Using join/collect to return task description when task is complete
Hi,
I am trying to create a formula that returns a collection of tasks descriptions when the task is marked as 100% complete. The overall goal is to show, per project phase, what tasks have been completed to date.
Here's what I have currently: =JOIN(COLLECT({Project Plan - EOL Asset Enterprise Range 1}, {Project Plan - EOL Asset Enterprise Range 4}, 1){Project Plan - EOL Asset Enterprise Range 5},",")
Project Plan - EOL Asset Enterprise Range 1 = project task names w/in the phase
Project Plan - EOL Asset Enterprise Range 4 = Task completion
Project Plan - EOL Asset Enterprise Range 5 = project task names w/in the phase
Am I on the right track here? I'm getting an Unparsable response.
Answers
-
Try this:
=JOIN(COLLECT({Project Plan - EOL Asset Enterprise Range 1}, {Project Plan - EOL Asset Enterprise Range 4}, @cell = 1), ", ")
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
Unfortunately, I'm getting an Incorrect Argument Set on the formula you shared above.
I added a column to my project plan to indicate phase so I would want to add that as a condition as well. Something like...
=JOIN(COLLECT({Project Plan - EOL Asset Enterprise Range 1}, {Project Plan - EOL Asset Enterprise Range 4}, @cell = 1, {Project Plan - EOL Asset Enterprise Range 6}, 1), ", ")
Where range 6 is the Phase # column
-
I think I got it. The formula that seems to be working is as follows...
=JOIN(COLLECT({Project Plan - EOL Asset Enterprise Range 1}, {Project Plan - EOL Asset Enterprise Range 4}, @cell = 1, {Project Plan - EOL Asset Enterprise Range 6}, @cell = 1), ", ")
I just added @cell= to the last criteria and updated the range reference to include the entire column for range 4.
-
@Alex Hackford Glad you were able to get it sorted.
The Incorrect Argument Set error would have most likely been coming from the ranges not being the same. If one is referencing an entire column, then they all should. Otherwise you will get that error.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives