Multiple Duration Fields
I'm attempting to track a duration time needed for our project manager and a separate duration time needed by the customer. I want to calculate those two separately. Some tasks require time for customer only; others for the project manager; others require involvement from both.
Is there a way to create two separate fields that track the work required by each separately?
Answers
-
Hi,
Its not currently possible, to have multiple duration columns (and duration column type is very specific to gantt views).
I would advice : to split the row into 2 rows.
Or to create/manage two classics texn/number columns and only record hours into them.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.5K Get Help
- 367 Global Discussions
- 202 Industry Talk
- 432 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 447 Show & Tell
- 29 Member Spotlight
- 1 SmartStories
- 285 Events
- 36 Webinars
- 7.3K Forum Archives