Multiple Duration Fields

I'm attempting to track a duration time needed for our project manager and a separate duration time needed by the customer. I want to calculate those two separately. Some tasks require time for customer only; others for the project manager; others require involvement from both.


Is there a way to create two separate fields that track the work required by each separately?

Answers

  • Etienne Mermillod
    Etienne Mermillod ✭✭✭✭✭

    Hi,

    Its not currently possible, to have multiple duration columns (and duration column type is very specific to gantt views).

    I would advice : to split the row into 2 rows.

    Or to create/manage two classics texn/number columns and only record hours into them.