Including Half Day Holiday to Timeline Nonworking Day

Is there a way to add half days as a holiday in a timeline (nonworking days)?
EX: We are having a half day on Friday and Monday off for Memorial Day.
I was hoping to find a way to include in this in the timeline (nonworking days)?
https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Answers
-
Hi @mpomerantz
There currently isn't a way to represent a day on a Gantt chart as a half-holiday; you will either need to define that day as a full holiday or a working day.
That said, if you keep that day as a "working day" and some of your tasks span over that date, you could adjust the duration to have .5 to represent this half day. (See: Project Sheet Columns: Start Date, End Date, Duration, % Complete and Predecessors)
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
-
Thank you Genevieve!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.2K Get Help
- 462 Global Discussions
- 155 Industry Talk
- 506 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 516 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives