Formula for task health
I am looking for a formula to identify task heath, based on duration, % complete and target due date, where the health is based on duration of task, such as 5d and if there is enough time to complete the task and the %completed - so a 10d task that is more than 10d before target date would be green. That same task would remain green if it were only a week prior as long as at least 50% of the task is complete. The color would change to yellow if the task is 5days or less out and the % is less than 50% complete, or if the task is up to 5d after the target date. Anything after that is red. if the project is on hold, then the color is amber.
green = %duration up to 50% before target due date
green = 50% > before duration and 50% > task completion
yellow = up to 1 week after target due date
yellow = %duration > 50 and task completion < 50%
red = more than one week after target due date
amber = hold
Answers
-
Try something like the following:
=IF(Status@row = "Hold", "Gray", IF(AND(TODAY() > WORKDAY([End Date]@row, 5), [% Complete]@row <> 1), "Red", IF(AND([% Complete]@row < 0.5, NETWORKDAYS([Start Date]@row, TODAY()) / Duration@row > 0.5), "Yellow", "Green")))
I'll break down what it says in order.
Gray Statement
There is no Status column that returns both a Yellow and an Amber status ball, but we can add a Gray ball in when the Status is on Hold. We want this to be the very first thing so the formula doesn't output any other colour if this word is in your Status cell:
=IF(Status@row = "Hold", "Gray",
Red Statement
=IF(AND(TODAY() > WORKDAY([End Date]@row, 5), [% Complete]@row <> 1), "Red",
First we tell the formula when to turn Red. This is only if it meets two criteria:
% Complete is not 100%
- [% Complete]@row <> 1
AND If Today is 5 Working Days past the End Date
- TODAY() > WORKDAY([End Date]@row, 5)
Yellow Statement
Then we can move on to Yellow:
IF(AND([% Complete]@row < 0.5, NETWORKDAYS([Start Date]@row, TODAY()) / Duration@row > 0.5), "Yellow",
If the % Complete is less than 50%
- [% Complete]@row < 0.5
AND If the number of working days from the Start of the task until Today is more than 50% of the Duration
- NETWORKDAYS([Start Date]@row, TODAY()) / Duration@row > 0.5
Green Statement
Finally, we can simply say that if none of the above criteria are met, the row is Green. This is because the formula will only get to this point if the row doesn't match any of the above criteria.
Let me know if this works for you!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 140 Just for fun
- 57 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!